The City’s Curb and Sidewalk Repair Program is designed to address damaged, deteriorating, or unsafe sections of concrete throughout our neighborhoods. As part of this ongoing initiative, city crews and contractors identify and remove areas affected by cracking, settling, or other surface issues. These sections are then replaced with new concrete that meets current safety and accessibility standards. This program helps maintain safe pedestrian pathways, improves neighborhood aesthetics, and supports long-term infrastructure health. The City is divided into four sections, with one section evaluated each year on a rotating basis. In addition, main roads and school routes are inspected annually to ensure safety and accessibility.



Tentative Start Date:May 22, 2025, weather dependent
Tentative Completion Date:September 1, 2025
Bid Opening:March 25, 2025
Project Manager:Brad Valentino, Street Superintendent
Contractor:Globe Construction, Inc.
Awarded Contract Amount:$193,000.00
Funding Source:Local Roads



Anticipated Hours of Work:

7:00 a.m.–6:00 p.m. Mon–Fri; 8:00 a.m.–5:00 p.m. Sat. (If necessary)