Plum Grove Drive/South Street Watermain Project

   
Tentative Start Date: May 2020
Tentative Completion Date: September 2020
Bid Opening: February 11, 2020
Project Manager: Jeff Stewart, RMPW Utilities Supervisor
Contractor: Mauro Sewer Construction
Awarded Contract Amount: $1,298,804.00
Funding Sources: City Bonds

Project Information

Replacement of existing cast iron water mains with new PVC pipe water mains, including new water service connections and service pipe to each residence, fire hydrants and complete pavement and ground surface restorations.

Construction Limits

Plum Grove Drive from Magnolia to Barker and South Street from Meadow Drive to Dove Street.  Driveway and street access may be impacted during the project. Every effort will be made to keep interruptions as few as possible.  All residents will have access to their driveways by the of the work day.

On-street parking within the work zone is not permitted during hours of construction (M-F: 7am - 6pm).  Please park in your driveway or on adjacent streets not under construction to allow contractor activities to proceed with out delay.

Please place refuse & recycle carts at normal location for collection prior to 6:00 am on your regularly schedule day of the week.  Refuse will be picked up before the start of construction in you area.

Project Updates

Week of 8/3/2020: This week, the City’s contractor, Mauro Sewer Construction, completed all the water main work on South Street from Meadow Drive to Dove Street. On Plum Grove Drive, the water main installation is complete, and disinfection and sample connection have begun.

Week of 08/10/2020: Next week, Mauro Sewer will begin concrete, asphalt and landscape restoration on South Street and South Court. Installation of water service lines will begin on Plum Grove Drive. Residents will continue to have knocks on their doors, notifying them of a 20-30 minute break in service to connect to the new service. This has been a seamless exercise so far, and will continue to be so, with minimal disturbance.

Traffic Controls will be maintained with new sites of barricades and cones. The public is asked to exercise patience when driving in the area where construction is actively going on. The public should also take note of any “No Parking” signs posted along Plum Grove Drive.