Euclid Avenue Multi-Use Path

   
Tentative Start Date: September 2018
Tentative Completion Date: May 2019
Bid Opening: 08/03/2018 (IDOT Letting)
Project Manager: Bill Suchecki, RMPW Street Maintenance Superintendent
Contractor: A Lamp Concrete Contractors, Inc.
Awarded Contract Amount: $448,668.85
Funding Sources: 80% State, 20% Local (Rolling Meadows & Arlington Heights

Project Information

The work to be performed consists of tree removal, earth excavation and embankment, curb and gutter removal and replacement, HMA pavement resurfacing, aggregate base course, HMA surface course, traffic signal modifications, fence removal and replacement, and parkway restoration and landscaping improvements.

Construction Limits

Euclid Avenue from Rohlwing to Salt Creek

Weekly Project Updates

Update as of 06/20/19: Landscaping plantings and parkway restoration completed. Upcoming work includes completion of fence installation by June 21, and traffic signal turn on at Salt Creek Lane on June 26.  Project completion is anticipated by end of June 2019.

Construction Notifications