Barker Avenue Bridge Superstructure Replacement

   
Tentative Start Date: May 2019
Tentative Completion Date: September 2019
Bid Opening: 1/18/2019 (IDOT Letting)
Project Manager: Bill Suchecki, RMPW Street Maintenance Superintendent
Contractor: Martam Construction, Inc.
Awarded Contract Amount: $613,256.50
Funding Sources: 80% State; 20% Local

Project Information

The work to be performed consists of removal of existing bridge superstructure, channel excavation and rip rap stabilization, placement of precast prestressed deck beams, concrete wearing surface, parapet walls, form liner abutment wall textured facing, approach pavement removal and replacement, guardrail replacement, and landscape restoration.

Construction Limits

Barker Avenue Bridge over Salt Creek



Barker Ave

Weekly Project Updates

Update as 11/22/19: Project is complete.

Construction Notifications