Arbor Drive Water Main Improvements Phase II

   
Tentative Start Date: April 3, 2020
Tentative Completion Date: June 15, 2020
Bid Opening: March 17, 2020
Project Manager: Dan Seveska, RMPW Utilities Superintendent
Contractor: Mauro Sewer Contruction
Awarded Contract Amount: $614,885.50
Funding Sources: Local, Utilities Fund

Project Information

The work includes the construction of approximately 1,826 feet of 12-inch ductile iron water main installation, approximately 160 feet of 6-inch water service lines, valves, vaults, fire hydrants, pavement patching, concrete curb and gutter removal and replacement, restoration, and all other incidental work.

Construction Limits

The project starts at the entrance to Arbor Drive from Algonquin Road, then eat and south and west approximately 1,826 feet, ending near the 4714 building on Arbor Drive.

arbordr

Weekly Project Updates:



Construction Notifications