Tentative Start Date: | April 2019 |
Tentative Completion Date: | August 2019 |
Bid Opening: | 02/28/2019 |
Project Manager: | Bill Suchecki, RMPW Street Maintenance Superintendent |
Contractor: | Arrow Road Construction Company |
Awarded Contract Amount: | $864,771.61 |
Funding Sources: | Local and MFT (Motor Fuel Tax) |
The work to be performed consists of storm sewer improvements, curb and gutter removal and replacement, sidewalk removal and replacement, asphalt surface removal, pavement base patching, asphalt leveling binder, asphalt surface course, signage removal and replacement and parkway restoration.
Hawk Lane (Meadow Drive to Dove Street)
Oriole Lane (Hawk Lane to Grouse Lane)
Wren Lane (Hawk Lane to Central Road)
Wren Court (Wren Lane to Terminus)
Central Road (Jay Lane to Weber Drive)
Cyndi Court (Old Wilke Road to Terminus)
Thrush Court (Thrush Lane to Terminus)
Eleanore Court (E. Frontage Road to Terminus)
Update as of 11/22/19: Project is complete